Capital & Campus Projects

Capital & Campus Projects: December 2025

By SPSCC Facilities

December 15, 2025

Current Projects

Soccer Field

  • The Master Plan work is complete, and we are moving full speed ahead with a new SPSCC Soccer Field.
  • We have submitted for permits through the city of Olympia.
  • Project is currently out to bid with bids set to open December 9th.

Building 34

  • We are working to finish tenant improvements for the classrooms on the first and second floors.
  • Work will begin in the first of the year.

Building 35

  • Project includes the replacement lab exhaust fan motor, controls upgrade, and retro-commissioning. This work will improve the heating and heating efficiency of the building.
  • We identified two issues that we are adding to the project to get fixed:
    • Changing out of the control cards and repair jam alarms.
    • Rebuild two boilers.
  • Work will be completed by the end of December.

Energy Efficient Lighting Project

  • Project is complete.

Building 22 Roof Leak

  • Working with the original installer to get the leaks in the building fixed.
  • Leaks have been narrowed down, and are still being worked on.

Angela Bowen Center Roof Leak

  • Leaks are fixed.

Building 23 MDF/IDF Cooling

  • The current system has not been operational for some time.
  • Will be replacing with a new Mitsubishi system.
  • Work to begin in the new year.

Building 20 Boiler replacement

  • Boilers are currently inoperable.
  • The building is being heated by temporary heaters throughout the building.
  • Working on securing funding and a contractor to get the replacement completed.

Projects on the Horizon

  • Building 25 Elevator Controls Upgrade
  • Retention Pond Replacement
  • Building 25 Entry Stairs