Master Plan Update
- Responses to city comments/questions finalized. Once the city approves the plan, it will be scheduled to go before the Hearings Examiner.
 - McGranahan - Matt Lane - is the consultant DES project manager is Essa Oro.
 - Project Parcel Number - 112828110500
 - Master Plan Update is currently available for review on the facilities website.
 
Building 25 - Business Office Renovation
- Electrical and mechanical work underway
 - Within the next 14 days Prime, texture, paint, installation of ceiling grid and fire equipment installations will be complete
 - Anticipated project completion late April
 - Furniture has been ordered, and ETA will be available shortly
 - No delays in timeline.
 
Building 27
- Project closeout underway
- Project funding sources exhausted
 
 
Building 34
- Grant funds ($617,624) will allow for the replacement of 14 additional heat pumps and a full upgrade to the building controls. Additional pumps ordered ETA is 3/24.
 - Ameresco is the ESCO company - Heather DeMunn and Nate Salyer the contacts. Cody Jacks is the DES project manager.
 - All framed walls complete.
 - Phase 1 demo and electrical near completion.
 - Plumbing Demo complete.
 - Electrical on schedule.
 - Low voltage on schedule.
 - No delays in the timeline.
 - CNA Program scheduled to temporarily relocate Bldg. 32.
 
Building 35
- MacDonald Miller is the ESCO company - Rob Wyllie and Ryan Haggerty are the primary contacts. Cody Jacks is the DES project manager.
 - Project includes the replacement of Heating Control Systems and Heating Valve updates.
 - This project will have three funding sources - a state allocation, local reserve funds and grant monies.
 - Projected schedule will have a start date of late March
 - June 30 deadline project deadline June 1 invoice deadline.
 
Building 21 Boiler/Cooling Tower Replacement
- Boiler installation complete
 - Cooling tower has been ordered and scheduled for 4/25 install
 - Communication Software and mobile app will be part of the final package.
 - Emergency funding ($225,535), grant funding ($440,509) and reallocated infrastructure money will cover this project
 - Cooling Tower hardware approved and ordered
 - Cooling Tower curb approved for reuse
 - Currently No Delays in Timeline.
 
Energy Management Programs
- Building 31 retro-commissioning to save energy program value $38K
 - DOC Grant reimbursement for Building 34, 35 and 21
 - Property wide survey and savings benefits underway. Anomaly Study.
 - Clean Buildings compliance. Operations and maintenance Program Energy management Program.
 - PSE COHORT Program
 - Building Operator Training
 
Energy Efficient Lighting Project
- A grant to cover the cost of replacing all non-LED lights ($1mill. building and site) on the Olympia campus has been awarded. Final contract from Amersesco Approved.
 - Approved contract re-negotiated and amended to not exceed total funding of $1 million. This will potentially create a $174,928 local cost savings.
 - Final buildings included in project will change to reflect the savings. Revised buildings on
project lists include Buildings 22, 25,27,34,35 and 1st floor of Building 16
Bldg. 20 & 23 upgrades will occur at a later date. - Ameresco is the ESCO company - Heather DeMunn and Nate Salyer the contacts. Cody Jacks is the DES project manager.
 - Sample lighting locations in Bldg. 34 will show conference, classroom and common area settings to be used campus wide. Currently available to view.
 
EV Charging Stations
- 10 chargers funded with grant/local money.
 - Five to be located in Lot C and 5 to be located in Lot J
 - Meeting set up with Forma/DES and EV Rep the week of the 17th.
 - ETA for installation is April
 - Two funding sources - local and grant money.
 - R779 is the allocation for the grant portion of the project ($75,000)
 - R778 is the allocation for the local match portion of the project ($25,000)
 
New Business and Key Projects
- Building 31 awarded a $38,000 Retro-Commissioning Audit! With the purpose of helping to extend the life of building systems and reduce environmental impact. project guidelines available.
 - Building 25 proposal in house to update the MDF Data Room HVAC. Coordinating new contractor process with DES
 - Kraken Studios underway with the construction of recording and sound stages. Studio design is complete. HVAC, Electrical scheduled.
 - ABC Rooftop currently being monitored for repairs schedule.
 - Two Boilers are being monitored in Bldg. 35. We currently are scheduling a complete rebuild but replacement in the near future will be inevitable.
 - Energy Management Program is currently underway with PSE. This will reward the college with cash savings for upcoming projects.